Business User News

In the news, we notify electrical energy market participants about all important events that could impact their operations.

07.03.2015 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 550 MW for delivery day 09.03.2015 from 06:00 to 24:00 due to the maintenance work in Austrian transmission grid. The NTC in remaining hours stays unchanged.  Read More

05.03.2015 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 700 MW for delivery day 07.03.2015 from 18:00 to 24:00 due to the expectation of high physical flows in Austrian transmission grid. The NTC in remaining hours stays unchanged.  Read More

05.03.2015 | Business user news

Please be informed that maintenance works scheduled for 05.03.2015 are finished. The Slovenian System Operator Scheduling application is now fully operative. Read More

04.03.2015 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 550 MW for delivery day 06.03.2015 from 00:00 to 20:00 due to the maintenance work in Austrian transmission grid. Read More

03.03.2015 | Business user news

Limitation of Intra-Day cross-border capacities allocation Read More

03.03.2015 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 550 MW for delivery day 05.03.2015 from 00:00 to 24:00 due to the maintenance work in Austrian transmission grid. Read More

03.03.2015 | Business user news

We would like to inform Market Participants that, as part of the early implementation project of the Network code on Forward Capacity Allocation, ENTSO-E has launched a web-based public consultation on Harmonised Allocation Rules for forward capacity allocation. All interested parties are strongly invited to submit their comments by 30 March 2015.Further details can be found on:https://www.entsoe.eu/news-events/announcements/announcements-archive/Pages/News/Consultation-on-the-Harmonised-Allocat... Read More

02.03.2015 | Business user news

Limitation of Intra-Day cross-border capacities allocation Read More

02.03.2015 | Business user news

We would like to inform market participants that on the request of Austrian Transmission System operator APG, NTC value in direction AT-SI will be reduced to 550 MW for delivery day 04.03.2015 from 00:00 to 24:00 due to the maintenance work in Austrian transmission grid. Read More

02.03.2015 | Business user news

Due to maintenance works on the Slovenian System Operator Scheduling application, the application will be stopped on 05.03.2015 between 09:20 and 11:30. In this period there will not be possible to make nominations of schedules for the day ahead and intra-day at all Slovenian borders. Confirmed schedules with delivery hours in the above mentioned period will remain unchanged. Read More

Page 213 of 331 First 211212[213]214215 Last