Single Day-Ahead Coupling (SDAC)- potential consequences of Brexit

Nominated Electricity Market Operators (NEMOs) and Transmission System Operators (TSOs) are prepared for a potential scenario where the United Kingdom leaves the EU without a deal on 31 October 2019. 
Should this scenario happen, the consequence would be the removal of Great Britain (GB) from implicit day-ahead market coupling. In that case the last implicit allocation on BritNed, IFA and Nemo Link would take place on 31 October (D-1), for delivery date 1 November (D). The first explicit allocation for day-ahead capacity on the BritNed, IFA and NemoLink interconnectors would take place on 1 November (D-1), for delivery date 2 November (D).

Official press release